Update: M11 junction 9 to 10: bridge repairs

I am writing to update you as we continue our work to replace the expansion joints, re-waterproof and resurface the M11 junction 9 overbridge. This work will ensure the bridge continues to remain in a safe and serviceable condition.

We plan to complete this work over 1 weekend from Friday 27 May, weather conditions permitting.

Closures and diversions

To carry out the work safely, there will be a 50mph speed restriction on the junction 9 overbridge and close the M11 between junctions 9 and 10 in both directions. Traffic will be diverted as follows:

  • M11 junction 10 to 9 southbound, full closure

Friday 27 May, 9pm to Monday 30 May, 5am

Southbound traffic will be diverted off the M11 at junction 10 onto the A505 / A11. Exit the A11 using the A1307 slip road and return onto the A11 southbound to re-join the M11 at junction 9. Northbound traffic will follow the same diversion but in reverse.

How to find out more

To find out more about road improvements we’re carrying out across the East of England, please visit our website at https://nationalhighways.co.uk/our-work/east/.

If you would like more information, please contact us on 0300 123 5000, or by email at  info@highwaysengland.co.uk.